LIGO Document E1400463-v5

aLIGO Installation Acceptance Document for WBSC9 (X)

Document #:
LIGO-E1400463-v5
Document type:
E - Engineering documents
Other Versions:
Abstract:
aLIGO Installation Acceptance Document for WBSC9.
Topics:
Keywords:
WBSC9
Notes and Changes:
WBSC9_acceptance_notes_2014-12-17 (S.Aston)

Change list from E1400463-v1 to v2

Section 1 (Installation)
- Electronics Rack Designations have now been populated for SUS and ISC. But, SEI & TCS are still missing.
- Noted that there is a temporary T240 Ground Seismometer at X end, in place of a STS-2 D1400077.

Section 2 (Procedures)
- Added OpLev aLOG links for installation, alignment and calibration.

Section 3 (Drawings)
- Added Electronics Rack Drawings for SUS, SEI and ISC.

Section 4 (Serial Numbers)
- Added ICS link for HEPI, D0901150, sub-assembly there of.

Section 5 (Testing)
- Viewports, removed link to old ICS record E1300447, replaced with more suitable T1200363, but still needs updating, and test status not shown.
- AOS/ACB, added photodiode tested in-situ using baffle OpLev alignment & calibration tests, aLOG link 10331.
- AOS/TCS/RHx, added initial testing link to aLOG 9272, but need acceptance testing measurements.
- TMSX, confirmed that no B&K measurements have been taken.
- ESD, added aLOG links to ESD initial and TF tests.

Section 6 (Installation Completeness)
- ICS assembly records to be updated.

Section 7 (Integration Issues / ECRs)
- I noticed there was an open integration issue regarding a noisy channel on the ETMX L2 UL OSEM (Bug#929).

Change list from E1400463-v2 to v3

Section 1 (Installation)
- Electronics Rack Designations have now been populated for the remaining SEI & TCS racks. Added hyper-links to DCC.
- Other equipment, added a DCC link showing placement of ground seismometer for X end.

Section 5 (Testing)
- Noted that testing is on TCS to-do list.

Section 7 (Integration Issues and ECRs)
- Added a link to integration issue container for WBSC9 (#987)

Change list from E1400463-v3 to v4

Preserved hyper-links in PDF document.

Section 3 (Drawings)
- Added Electronics Rack Drawings for SUS, SEI and ISC as well as TCS.

Section 7 (Integration Issues and ECRs)
- Removed an out of date comment noting that this was still the LLO buglist.

Change list from E1400463-v4 to v5

Section 5 (Testing)
- Added note to AOS/CMB B&K testing stating that links are to equivalent LLO measurements, but no LHO measurements have been found.

Section 6 (Installation Completeness)
- Amended note to state that all items are installed.
- Removed note regarding ICS completeness.

Related Documents: