LIGO Document E1200040-v2
- This document provides links to the acceptance documentation for all aLIGO PSLs, in particular PSL #2 installed at LHO (initially installed in the H2 location and later moved to the H1 location)).
It is a replacement for the template E1300457 used in the acceptance process of other subsystems.
- PSL-H1 and 3rd. Ifo. 14-Aug-2014, Acceptance Review Team (Rich Abbott, Dennis Coyne, Peter Fritschel, Valera Frolov, Marty Levine, Rick Savage - chair) have provisionally accepted the PSL-H1 and PSL-3rd Ifo. There are some minor actions yet to be completed (which are listed in the "punch list" document L1400133).
Systems Engineering has reviewed and accepted this Fabrication Acceptance Review as well.
updated Phase 1 testing links for OBS 2 and OBS3
added links to some more manuals
DCC Version 3.4.3, contact
Document Database Administrators