Event Listing

Events moderated by Steve Marroquin of LIGO - California Institute of Technology

DateTimeTitle LocationTopic(s)
15 Jul 201509:00 – Met One: Model GT521S Particle Counter
None
13 Jul 201509:00 – Global Technical Services: Ion Pump Conduit and Cable Installation
None
08 Jul 201509:00 – DC-208: LHO DCS Fire Suppression and UPS
None
24 Jun 201509:00 – LLO Liquid Nitrogen: FY16-FY18
None
 09:00 – LHO Liquid Nitrogen: FY16-FY18
None
05 Jun 201509:00 – NeoLase Frontend Diodebox
None
03 Jun 201509:00 – Xlerant Implementation and Subscription Service
None
01 Jun 201509:00 – DC-606: Computer Disk Storage
None
19 May 201509:00 – Prudential: Garb/Cover Cleaning at LLO and LHO
None
18 May 201509:00 – Fine TecDC-601c- (MicroCloud) (DC-O1 Cluster) Quote 1
None
 09:00 – Fine Tec DC-601d- (Twin Pro2 Cluster Servers and Cluster Nodes) (DC-O1 Cluster) Quote 3
None
 09:00 – ASA Computers DC-618b- (Commodity GPU Card (DC-O1 GPU) Quote 4
None
 09:00 – FINE TEC DC-618a- (GPU Node and GPU Spare Parts Kit) (DC-01) Quote 2:
None
01 May 201509:00 – DC-601b (DCS First Article Cluster Order: Twin Pro 2 and GPU)
None
 09:00 – DC-601a (DCS First Article Cluster Order: MicroCloud)
None
28 Apr 201509:00 – Power Distribution Units (PDU's): Anixter; DC-207-LLO, DC-208-LHO, Caltech
None
20 Apr 201509:00 – LIGO Livingston Sewerage and Wastewater Systems Maintenance
None
15 Apr 201509:00 – Source One: Inventory and Logistics Support: Natividad
None
25 Feb 201509:00 – Kepco: DC SuppliesKEPCO Inc 75ADV-S231885
None
23 Feb 201509:00 – Mid-Columbia Engineering Inc.: Budget Analyst
None
13 Feb 201509:00 – Probe laser for characterizing the vertex cavitiesJDS Uniphase Corp 75ADV-S230663
None
12 Feb 201509:00 – Sage Inc.; Machined components for TMDS structural support
None
10 Feb 201509:00 – Opto-Sigma: Prod Motor Stages Controllers
None
26 Jan 201509:00 – VAT Inc.: UHV Gate Valves
None
23 Jan 201509:00 – Microsemi Frequency and Time Corp: Atomic Clocks
None
 09:00 – Mad City Labs: implement auto-centering for the green WFS
None
20 Jan 2015All day/no time
None
 09:00 – 09:30Getter Pumps (SAES Group):Basic Procurement Documents -Non-Comp
None
 09:00 – Phase II of Test Mass Discharge System (TMDS): Gamma Vacuum
None
13 Jan 2015All day/no timeSAVARD 75-1096027
None
 09:00 – LLO Beam Tube Washing:RFQ
None
08 Jan 201509:00 – LHO Beam Tube Cleaning (APOLLO)
None
30 Dec 201409:00 – MicroSense LLC: Vacuum Compatible Capacitive Position Sensors
None
08 Dec 201409:00 – Zygo: Polishing of Two Compensation Plates
Core Optics
26 Nov 201409:00 – (MKS) Pirani Gauge for Surface Charge Control Ionizer
None
24 Nov 201409:00 – AO-901: Balance of viewports needed for aLIGO 3rd IFO at LHO
None
07 Nov 201409:00 – ManPower Corporation: Rodica Martin
None
24 Oct 201409:00 – DC-207b: Liebert - Computer Conditioning
Procurements
23 Sep 201409:00 – DC-207a: DCS LLO Facilities for I.T Room
None
17 Sep 201409:00 – DC-208a; LHO DCS Facility Room Air Conditioning
None
16 Sep 201409:00 – Jay Copti: Electronics Technician; Aerotek (Caltech)
None
10 Sep 201409:00 – Tomeeka Lewis: Research Support Technician; Ammons Staffing Inc. (LLO)
None
 09:00 – Shanan Schatzle: Consultant; LLO
None
 09:00 – Tomeeka Lewis: Technical Cleaner; Ammons Staffing Inc. (LLO)
None
 09:00 – Richard Bagley: Consultant: LLO
None
 09:00 – Sydney Meshkov: Consultant; Caltech
None
 09:00 – Stacie Price: Custodial; Ammons Staffing Inc. (LLO)
None
 09:00 – Rai Weiss: Consultant; Caltech
None
 09:00 – Fred Asiri: Consultant; Caltech
None
28 Aug 201409:00 – Procurement Status Report for Operations and ALIGO
None
 09:00 – Procurement Status Report for Operations and Advanced LIGO
None
22 Aug 201409:00 – LLO Recycling Scrap Contract with Florida Parish Industrial
None
19 Aug 201409:00 – DC-112a: SIZELER BROWN THOMAS: DCS LLO Facilities for I.T Room
Procurements
01 Aug 2014All day/no time
None
 09:30 – 11:00Syracuse University: Ops DCS Optimization Support: (D. Brown); 75-1095335:Subcontact
None
18 Jul 2014All day/no time
None
 09:00 – Abilene Christian University: DCS Optimization Support: (J. Willis); 75ADV-1095357
None
 09:30 – 11:30Abilene Christian University: DCS Optimization Support: (J. Willis); 75ADV-1095357:Invoices
None
23 Jun 201409:00 – DCS For Installation of Computer Racks and Subfloor Installation at Caltech
None
05 May 201409:00 – Integration and Testing Support May 15th 2014 to March 31, 2014Univ Massachusetts 75ADV-1095164 UMASS
None
01 Apr 2014All day/no timeDylan Investment 75-S194585
Operations
 09:00 – 12:00LHO Warehouse Lease:Basic PO Documents
Operations
25 Mar 201409:00 – Joe Gleason: Manpower Inc.
None
21 Jan 201409:00 – StorageTek Tape Analytics: Edge Solutions
None
19 Nov 201309:00 – Stop Work Order_Termination Clause Documentation
None
29 Oct 2013All day/no time75ADV-S184747
None
 09:00 – 09:30Matrix Consulting Inc: Craig Whiteley:RFQ/ProposalLHO
None
28 Aug 2013All day/no time75ADV-
None
13 Aug 2013All day/no time75ADV-
None
03 Jul 2013All day/no time75ADV-
None
19 Jun 2013All day/no time75ADV-
None
12 Jun 2013All day/no time75ADV-
None
10 Jun 2013All day/no time75ADV-
None
07 Jun 2013All day/no time75ADV-
None
01 Jun 2013All day/no timeColumbia Univ 75ADV-1094081
None
09 May 2013All day/no time75ADV-
None
06 May 2013All day/no time75ADV-
None
17 Apr 2013All day/no timeSyracuse Univ 75ADV-1093854
None
06 Mar 2013All day/no time75ADV-S070362
None
28 Feb 201309:00 – 10:00SI-134a: BSC and HAM ISI in-vacuum cable & clamp hardware (PO#S073886):Procurement Documents75ADV-S073886
None
27 Feb 2013All day/no time75ADV-S1086727
None
 All day/no time75ADV-S1086233
Procurements
 All day/no time75-S161559
Seismic Isolation
 All day/no time75ADV-S1085992
None
 All day/no time75ADV-S070362
None
 09:00 – 09:30SI-101: HEPI position sensors
Seismic Isolation
 09:00 – SI-147a: HAM ISI Maraging Steel Blades:Procurement Documents
None
 09:00 – 09:30SI-136: GS-13 Seismometers :Basic Procurement
None
 09:00 – SI-106: HEPI housing :Basic Procurement Docs
Procurements
 09:00 – SI-109: HEPI hydraulic actuator assemblies :Basic Procurement
None
08 Feb 2013All day/no time75ADV-
Personnel
Procurements
22 Jan 2013All day/no time75ADV-
Personnel
Procurements
16 Jan 2013All day/no time75ADV-S1093530
Personnel
Procurements
09 Jan 2013All day/no time75ADV-
Personnel
Procurements
21 Dec 2012All day/no time75ADV-
Personnel
Procurements
05 Nov 2012All day/no time75ADV-
Personnel
Procurements
02 Nov 2012All day/no time75ADV-
Personnel
Procurements
 All day/no time75ADV-
Personnel
Procurements
26 Oct 2012All day/no time75ADV-
Personnel
Procurements
15 Oct 2012All day/no time75ADV
None
08 Oct 2012All day/no time75ADV
None
20 Sep 2012All day/no time75ADV
None
15 Aug 201209:00 – Electrical Maintenance Contract - LLOLLO
Caltech
Observatory Facilities
10 Jul 2012All day/no time75ADV
None
28 Jun 2012All day/no time75ADV
Seismic Isolation
14 Jun 2012All day/no time75ADV-S144828
System Engineering
27 Apr 2012All day/no time75ADV
Auxiliary Optics
Procurements
 All day/no time75ADV
Auxiliary Optics
Procurements
23 Apr 2012All day/no time75ADV
Auxiliary Optics
Procurements
18 Apr 2012All day/no time75ADV
Procurements
02 Apr 2012All day/no time75ADV
Auxiliary Optics
Procurements
 09:00 – AO-556 Photonic Calibration Lasers:Change Orders / Modifications
Procurements
 09:00 – 09:30AO-556 Photonic Calibration Lasers:Bid Evaluation
Procurements
 09:00 – AO-556 Photonic Calibration Lasers:Technical Documentation
Procurements
 09:00 – AO-556 Photonic Calibration Lasers:RFQ
Procurements
 09:00 – 11:30AO-556 Photonic Calibration Lasers:Contract/PO
Procurements
05 Mar 2012All day/no time
Personnel
Procurements
 09:00 – 10:30Support Services - Esther Cunningham:Procurement Justification
Procurements
 09:00 – Support Services - Esther Cunningham:Basic
Procurements
 09:00 – Support Services - Esther Cunningham:Proposal/Statement of Work/Quote
Procurements
28 Feb 2012All day/no time75ADV-S141679
Procurements
 09:00 – 09:30FM_IN-502 Laundering and Maintenance of C-3 Cleanroom Garb and Covers:Technical Documentation
Procurements
 09:00 – 10:30FM_IN-502 Laundering and Maintenance of C-3 Cleanroom Garb and Covers:Change Order 1
Procurements
 09:00 – 09:30FM_IN-502 Laundering and Maintenance of C-3 Cleanroom Garb and Covers:RFQ
Procurements
 09:00 – 11:00FM_IN-502 Laundering and Maintenance of C-3 Cleanroom Garb and Covers:Bid Evaluation
Procurements
 09:00 – 12:30FM_IN-502 Laundering and Maintenance of C-3 Cleanroom Garb and Covers:Contract/PO
Procurements
21 Dec 2011All day/no time75ADV-S131790
Procurements
 All day/no timePraxair 75-S134773
Procurements
 09:00 – 13:00LHO Liquid Nitrogen FY12-FY14 Annual:Bid Evaluation and Procurement Justification
Procurements
 09:00 – Reiboldt: PSL Laser Enclosure for H-1:Change Orders / Modifications
Procurements
 09:00 – Reiboldt: PSL Laser Enclosure for H-1:Technical Documentation
Procurements
 09:00 – Reiboldt: PSL Laser Enclosure for H-1:RFQ
Procurements
 09:00 – 10:30LHO Liquid Nitrogen FY12-FY14 Annual:RFQ No. GS-004
Procurements
 09:00 – 10:30Reiboldt: PSL Laser Enclosure for H-1:Contract/PO
Procurements
 09:00 – 10:30LHO Liquid Nitrogen FY12-FY14 Annual:PO 75-S134773 Basic PO
Procurements
 09:00 – 10:00LHO Liquid Nitrogen FY12-FY14 Annual:Mod-1 Add Funds
Procurements
 09:00 – 10:30Reiboldt: PSL Laser Enclosure for H-1:Bid Evaluation
Procurements
07 Nov 201109:00 – 09:30LHO Tumbleweed Landscaping:Statement of Work
Procurements
 09:00 – 13:00LHO Tumbleweed Landscaping:Procurement Documentation
Procurements
 09:00 – 10:30LHO Tumbleweed Landscaping:Mod-1 FY2012 Authoriztion
Procurements
 09:00 – 09:30LHO Tumbleweed Landscaping:RFQ No. SM-038
Procurements
 09:00 – 10:00LHO Tumbleweed Landscaping:Quote Evaluation
Procurements
01 Oct 2011All day/no timeYamilet 75-S130810
Procurements
 All day/no time75ADV-S128536
Procurements
 09:00 – 10:30LLO Storage Rental:Change Order 1
Procurements
 09:00 – LLO Storage Rental:Technical Documentation
Procurements
 09:00 – LLO Storage Rental:RFQ
Procurements
 09:00 – 12:30LLO Storage Rental:Contract/PO
Procurements
 09:00 – LLO Storage Rental:Bid Evaluation
Procurements
08 Sep 2011All day/no time75ADV-S
Procurements
 09:00 – FM-165 Pilot Test: Vacuum Bake and Hydrocarbon Residual Gas Array:Change Order 1
Procurements
 09:00 – FM-165 Pilot Test: Vacuum Bake and Hydrocarbon Residual Gas Array:Contract/PO
Procurements
 09:00 – FM-165 Pilot Test: Vacuum Bake and Hydrocarbon Residual Gas Array:RFQ
Procurements
 09:00 – FM-165 Pilot Test: Vacuum Bake and Hydrocarbon Residual Gas Array:Bid Evaluation
Procurements
 09:00 – FM-165 Pilot Test: Vacuum Bake and Hydrocarbon Residual Gas Array:Technical Documentation
Procurements
06 Sep 2011All day/no time75ADV-S126196
Procurements
 09:00 – 09:30SI-134g In-Vacuum Cables:Technical Documentation
Procurements
 09:00 – 09:30SI-134g In-Vacuum Cables:RFQ
Procurements
 09:00 – 10:30SI-134g In-Vacuum Cables:Bid Evaluation
Procurements
 09:00 – 12:00SI-134g In-Vacuum Cables:Change Order 1
Procurements
 09:00 – 10:30SI-134g In-Vacuum Cables:Contract/PO
Procurements
15 Aug 2011All day/no time75ADV-S123273
Procurements
 09:00 – QinetiQ North America Inc. - Repair of ALIGO Actuators:RFQ
Procurements
 09:00 – 11:30QinetiQ North America Inc. - Repair of ALIGO Actuators:Contract/PO
Procurements
 09:00 – QinetiQ North America Inc. - Repair of ALIGO Actuators:Technical Documentation
Procurements
 09:00 – QinetiQ North America Inc. - Repair of ALIGO Actuators:Change Order 1
Procurements
 09:00 – 09:30QinetiQ North America Inc. - Repair of ALIGO Actuators:Bid Evaluation
Procurements
11 Jul 2011All day/no time75ADV-S115511
Procurements
 09:00 – 11:00FM-156 BSC Floor Assembly:Change Order 1
Procurements
 09:00 – FM-156 BSC Floor Assembly:RFQ
Procurements
 09:00 – FM-156 BSC Floor Assembly:Bid Evaluation
Procurements
 09:00 – FM-156 BSC Floor Assembly:Technical Documentation
Procurements
 09:00 – FM-156 BSC Floor Assembly:Contract/PO
Procurements
27 Jun 2011All day/no time75ADV-S121821
Procurements
 All day/no time75ADV-S122672
Procurements
 09:00 – 11:30AO-130 Viewport Clamps and Flanges:Bid Evaluation
Procurements
 09:00 – 10:00AO-131 Wedged Windows:RFQ
Procurements
 09:00 – AO-131 Wedged Windows:Change Orders
Procurements
 09:00 – 11:30AO-131 Wedged Windows:Contract/PO
Procurements
 09:00 – 09:30AO-130 Viewport Clamps and Flanges:RFQ
Procurements
 09:00 – 11:30AO-131 Wedged Windows:Bid Evaluation
Procurements
 09:00 – 09:30AO-130 Viewport Clamps and Flanges:Technical Documentation
Procurements
 09:00 – 09:30AO-130 Viewport Clamps and Flanges:Change Order 1
Procurements
 09:00 – 11:00AO-130 Viewport Clamps and Flanges:Contract/PO
Procurements
22 Jun 2011All day/no time
Laser Systems
Procurements
 All day/no time75ADV-S121590
Procurements
 09:00 – 09:30PS-140: H2 PSL Laser Diode and Chiller Rooms:Technical Documentation
Procurements
 09:00 – 10:00AO-120 Mode Cleaner Tube Baffle Assembly:Bid Evaluation
Procurements
 09:00 – 10:00PS-140: H2 PSL Laser Diode and Chiller Rooms:Bid Evaluation
Procurements
 09:00 – 09:30PS-140: H2 PSL Laser Diode and Chiller Rooms:RFQ
Procurements
 09:00 – 09:30AO-120 Mode Cleaner Tube Baffle Assembly:Technical Documentation
Procurements
 09:00 – 09:30AO-120 Mode Cleaner Tube Baffle Assembly:RFQ
Procurements
 09:00 – 11:00PS-140: H2 PSL Laser Diode and Chiller Rooms:Contract/PO
Procurements
 09:00 – 11:00AO-120 Mode Cleaner Tube Baffle Assembly:Contract/PO
Procurements
 09:00 – PS-140: H2 PSL Laser Diode and Chiller Rooms:Change Orders
Procurements
 09:00 – 11:00AO-120 Mode Cleaner Tube Baffle Assembly:Change Order 1
Procurements
02 Jun 2011All day/no time
Procurements
 09:00 – 09:30FM-150C -H2 Electronics Building HVAC:Technical Documents
Procurements
 09:00 – FM-150C -H2 Electronics Building HVAC:Change Order 1
Procurements
 09:00 – FM-150C -H2 Electronics Building HVAC:RFQ/RFP
Procurements
 09:00 – 09:30FM-150C -H2 Electronics Building HVAC:Bid Evaluation
Procurements
 09:00 – 10:30FM-150C -H2 Electronics Building HVAC:Contract / PO
Procurements
26 May 2011All day/no time
Procurements
 09:00 – 11:30Hamilton Metalcraft: Power Strip:Contract / PO
Procurements
 09:00 – Hamilton Metalcraft: Power Strip:Change Order 1
Procurements
 09:00 – Hamilton Metalcraft: Power Strip:Technical Documents
Procurements
 09:00 – Hamilton Metalcraft: Power Strip:RFQ/RFP
Procurements
 09:00 – 09:30Hamilton Metalcraft: Power Strip:Bid Evaluation
Procurements
25 May 2011All day/no time
Procurements
 All day/no time
Procurements
 09:00 – 09:30Fabrication of HSTS, HLTS and OFI Spacers:RFQ/RFP
Procurements
 09:00 – 11:00Fabrication of HAM Table Dog Clamps :Contract / PO
Procurements
 09:00 – 09:30Fabrication of HAM Table Dog Clamps :Bid Evaluation
Procurements
 09:00 – Fabrication of HSTS, HLTS and OFI Spacers:Change Order 1
Procurements
 09:00 – 09:30Fabrication of HAM Table Dog Clamps :RFQ/RFP
Procurements
 09:00 – Fabrication of HSTS, HLTS and OFI Spacers:Bid Evaluation
Procurements
 09:00 – 09:30Fabrication of HSTS, HLTS and OFI Spacers:Technical Documents
Procurements
 09:00 – 09:30Fabrication of HAM Table Dog Clamps :Technical Documents
Procurements
 09:00 – 10:30Fabrication of HSTS, HLTS and OFI Spacers:Contract / PO
Procurements
 09:00 – 11:00Fabrication of HAM Table Dog Clamps :Change Order 1
Procurements
24 May 201109:00 – Power Supplies and Racks for PSL Infrastructure:RFQ/RFP
Procurements
 09:00 – Power Supplies and Racks for PSL Infrastructure:Bid Evaluation
Procurements
 09:00 – Power Supplies and Racks for PSL Infrastructure:Contract / PO
Procurements
 09:00 – Power Supplies and Racks for PSL Infrastructure:Technical Documents
Procurements
 09:00 – 12:00Power Supplies and Racks for PSL Infrastructure:Change Order 1
Procurements
09 May 2011All day/no time75ADV-S116260
Procurements
 09:00 – Excel Contractors Inc. - Scottie Roberts:Proposal
Procurements
 09:00 – Excel Contractors Inc. - Scottie Roberts:Contract
Procurements
 09:00 – Excel Contractors Inc. - Scottie Roberts:Modifications
Procurements
25 Apr 2011All day/no time75ADV-S115491
Procurements
 09:00 – 12:00Support Services Labor Contract - George Retana:Change Order 1
Procurements
 09:00 – Support Services Labor Contract - George Retana:Close Out
Procurements
 09:00 – 09:30Support Services Labor Contract - George Retana:Contract
Procurements
 09:00 – Support Services Labor Contract - George Retana:Correspondence
Procurements
 09:00 – 09:30Support Services Labor Contract - George Retana:Proposal
Procurements
 09:00 – 13:00Support Services Labor Contract - George Retana:Invoices
Procurements
13 Apr 2011All day/no time75ADV-
Procurements
 09:00 – 10:00SI-131 and SI-161 Cable Bracket Assembly for Ham and BSC:Bids & Evaluation
Procurements
 09:00 – 09:30SI-131 and SI-161 Cable Bracket Assembly for Ham and BSC:RFQ/RFP
Procurements
 09:00 – SI-131 and SI-161 Cable Bracket Assembly for Ham and BSC:Change Orders
Procurements
 09:00 – 11:00SI-131 and SI-161 Cable Bracket Assembly for Ham and BSC:Contract / PO
Procurements
 09:00 – SI-131 and SI-161 Cable Bracket Assembly for Ham and BSC:Technical Documents
Procurements
11 Mar 2011All day/no time75ADV-S106199
None
 09:00 – 11:00Faraday Rotator and TGG Crystal:Change Order 1
Procurements
 09:00 – Faraday Rotator and TGG Crystal:RFQ
Procurements
 09:00 – 09:30Faraday Rotator and TGG Crystal:Bid Evaluation
Procurements
 09:00 – Faraday Rotator and TGG Crystal:Technical Documents
Procurements
 09:00 – 09:30Faraday Rotator and TGG Crystal:Contract/PO
Procurements
02 Mar 2011All day/no time75ADV-S111799
Procurements
 09:00 – 10:00Micro Laser Systems, Inc: Optical Lasers:Bids & Evaluation
Procurements
 09:00 – Micro Laser Systems, Inc: Optical Lasers:Change Orders
Procurements
 09:00 – Micro Laser Systems, Inc: Optical Lasers:RFQ/RFP
Procurements
 09:00 – 11:00Micro Laser Systems, Inc: Optical Lasers:Contract/PO
Procurements
 09:00 – Micro Laser Systems, Inc: Optical Lasers:Technical Documents
Procurements
24 Feb 2011All day/no time75ADV-S111261
Procurements
 09:00 – SI-134F BSC ISI Cable Wire:Change Orders
Procurements
 09:00 – SI-134F BSC ISI Cable Wire:Technical Documents
Procurements
 09:00 – 11:00SI-134F BSC ISI Cable Wire:Contract/PO
Procurements
 09:00 – 10:00SI-134F BSC ISI Cable Wire:Bids & Evaluation
Procurements
 09:00 – SI-134F BSC ISI Cable Wire:RFQ/RFP
Procurements
14 Feb 2011All day/no time75ADV-S111125
System Engineering
 09:00 – 12:00EPL Holdings, LLC - Calvin Jones:Contract
Procurements
 09:00 – 11:00EPL Holdings, LLC - Calvin Jones:Change Order 1
Procurements
 09:00 – EPL Holdings, LLC - Calvin Jones:Proposal
Procurements
 09:00 – EPL Holdings, LLC - Calvin Jones:Correspondence
Procurements
07 Feb 2011All day/no time75ADV-S111566
Procurements
 All day/no time
Procurements
 09:00 – SI-186 - Fabrication of Machined Table Masses for BSC-ISI:Change Orders & Modifications
Procurements
 09:00 – SI-195J - Fabrication of Machined Wall Masses and Keel Weights for BSC-ISI:Technical Documentation
Procurements
 09:00 – 11:00SI-195J - Fabrication of Machined Wall Masses and Keel Weights for BSC-ISI:Bid Evaluation
Procurements
 09:00 – SI-186 - Fabrication of Machined Table Masses for BSC-ISI:Technical Documentation
Procurements
 09:00 – 09:30SI-195J - Fabrication of Machined Wall Masses and Keel Weights for BSC-ISI:RFQ / RFP
Procurements
 09:00 – 11:00SI-186 - Fabrication of Machined Table Masses for BSC-ISI:Bid Evaluation
Procurements
 09:00 – 11:30SI-195J - Fabrication of Machined Wall Masses and Keel Weights for BSC-ISI:Contract / PO
Procurements
 09:00 – 09:30SI-186 - Fabrication of Machined Table Masses for BSC-ISI:RFQ / RFP
Procurements
 09:00 – 11:00SI-186 - Fabrication of Machined Table Masses for BSC-ISI:Contract / PO
Procurements
 09:00 – SI-195J - Fabrication of Machined Wall Masses and Keel Weights for BSC-ISI:Change Orders & Modifications
Procurements
03 Feb 2011All day/no time
Procurements
 All day/no time75ADV-S096174
None
 09:00 – SI-195H-2 - Fabrication of Magnetic Shields for BSC ISI GS-13 Pods:Change Orders & Modifications
Procurements
 09:00 – Ethos USA - Jesse Wiley:Proposal
Procurements
 09:00 – 10:30SI-195H-2 - Fabrication of Magnetic Shields for BSC ISI GS-13 Pods:Bid Evaluation
Procurements
 09:00 – 10:30SI-195H-2 - Fabrication of Magnetic Shields for BSC ISI GS-13 Pods:Contract / PO
Procurements
 09:00 – SI-195H-2 - Fabrication of Magnetic Shields for BSC ISI GS-13 Pods:Technical Documentation
Procurements
 09:00 – Ethos USA - Jesse Wiley:Contract
Procurements
 09:00 – Ethos USA - Jesse Wiley:Change Order 1
Procurements
 09:00 – 09:30SI-195H-2 - Fabrication of Magnetic Shields for BSC ISI GS-13 Pods:RFQ / RFP
Procurements
13 Jan 2011All day/no time75ADV-S109564
Procurements
 09:00 – 11:30SU-231 - ALIGO SUS Various Cables:RFQ / RFP
Procurements
 09:00 – SU-231 - ALIGO SUS Various Cables:Technical Documentation
Procurements
 09:00 – 11:30SU-231 - ALIGO SUS Various Cables:Contract / PO
Procurements
 09:00 – 11:30SU-231 - ALIGO SUS Various Cables:Bid Evaluation
Procurements
 09:00 – 11:00SU-231 - ALIGO SUS Various Cables:Supplemental Agreement #1
Procurements
04 Jan 2011All day/no time75ADV-S108127 CIT; S108220 LHO; S108235 LLO
Procurements
 All day/no time75ADV-
Procurements
 09:00 – ISC- ADC and DAC Boards:Bids & Evaluation
Procurements
 09:00 – Opto-Sigma: Tip-Tilt Micrometric Units and Stepper Motor Translators:RFQ/RFP
Procurements
 09:00 – Opto-Sigma: Tip-Tilt Micrometric Units and Stepper Motor Translators:Technical Documents
Procurements
 09:00 – ISC- ADC and DAC Boards:Contract / PO
Procurements
 09:00 – ISC- ADC and DAC Boards:RFQ/RFP
Procurements
 09:00 – 13:30Opto-Sigma: Tip-Tilt Micrometric Units and Stepper Motor Translators:Contract / PO
Procurements
 09:00 – ISC- ADC and DAC Boards:Change Orders
Procurements
 09:00 – Opto-Sigma: Tip-Tilt Micrometric Units and Stepper Motor Translators:Bids & Evaluation
Procurements
 09:00 – Opto-Sigma: Tip-Tilt Micrometric Units and Stepper Motor Translators:Change Orders
Procurements
 09:00 – ISC- ADC and DAC Boards:Technical Documents
Procurements
13 Dec 2010All day/no time75ADV-S108004
Procurements
 09:00 – 11:30Think Resources: Geneva Wilton:Contract
Procurements
 09:00 – 10:30Think Resources: Geneva Wilton:Change Order 1
Procurements
 09:00 – 09:30Think Resources: Geneva Wilton:Proposal
Procurements
18 Nov 2010All day/no time75ADV-1090045
Procurements
 All day/no time75ADV-1090080
Procurements
 09:00 – 11:00Recycle LHO:Contract / PO
Procurements
 09:00 – 10:00Recycle LHO:Bid Evaluation
Procurements
 09:00 – 09:30Recycle LLO:RFQ / RFP
Procurements
 09:00 – 10:30Recycle LLO:Payments
Procurements
 09:00 – 11:00Recycle LLO:Change Order 1
Procurements
 09:00 – Recycle LLO:Technical Documentation
Procurements
 09:00 – 10:00Recycle LLO:Bid Evaluation
Procurements
 09:00 – 11:30Recycle LHO:Change Order 1
Procurements
 09:00 – Recycle LHO:RFQ / RFP
Procurements
 09:00 – Recycle LHO:Technical Documentation
Procurements
 09:00 – 10:30Recycle LLO:Contract / PO
Procurements
08 Nov 2010All day/no time
Procurements
 09:00 – SU-110a Fabrication of SUS Quad Storage Containers:Change Orders
Procurements
 09:00 – 09:30SU-110a Fabrication of SUS Quad Storage Containers:RFQ / RFP
Procurements
 09:00 – 10:00SU-110a Fabrication of SUS Quad Storage Containers:Bid Evaluation
Procurements
 09:00 – SU-110a Fabrication of SUS Quad Storage Containers:Technical Documentation
Procurements
 09:00 – 11:00SU-110a Fabrication of SUS Quad Storage Containers:Contract / PO
Procurements
01 Nov 2010All day/no time75ADV-S107986
Procurements
12 Oct 2010All day/no time75ADV-S102404
None
 09:00 – 11:00Think Resources Labor Contract - Edmond Merilh:Contract
Procurements
 09:00 – Think Resources Labor Contract - Edmond Merilh:Correspondence
Procurements
 09:00 – Think Resources Labor Contract - Edmond Merilh:Modifications
Procurements
 09:00 – 09:30Think Resources Labor Contract - Edmond Merilh:Proposal
Procurements
08 Oct 2010All day/no time75ADV-S102114
None
 09:00 – 12:00Think Resources Labor Contract - Virginia Brocato:Change Order 1
Procurements
 09:00 – 11:00Think Resources Labor Contract - Virginia Brocato:Proposal
Procurements
 09:00 – 09:30Think Resources Labor Contract - Virginia Brocato:Correspondence
Procurements
 09:00 – 12:30Think Resources Labor Contract - Virginia Brocato:Contract
Procurements
08 Sep 2010All day/no time75ADV-S100214
Procurements
 09:00 – 09:30AO-236 TCS Ring Heater Assembly Components:RFQ / RFP
Procurements
 09:00 – 10:30AO-236 TCS Ring Heater Assembly Components:Contract / PO
Procurements
 09:00 – AO-236 TCS Ring Heater Assembly Components:Technical Documentation
Procurements
 09:00 – AO-236 TCS Ring Heater Assembly Components:Change Orders & Modifications
Procurements
 09:00 – 10:00AO-236 TCS Ring Heater Assembly Components:Bid Evaluation
Procurements
02 Sep 2010All day/no time75ADV-S105850
Procurements
 09:00 – 11:30AO-132 Fabrication of Pylons for ALIGO Optical Lever:Change Order 1
Procurements
 09:00 – AO-132 Fabrication of Pylons for ALIGO Optical Lever:Technical Documentation
Procurements
 09:00 – 12:30AO-132 Fabrication of Pylons for ALIGO Optical Lever:Bid Evaluation
Procurements
 09:00 – 10:00AO-132 Fabrication of Pylons for ALIGO Optical Lever:RFQ / RFP
Procurements
 09:00 – 11:30AO-132 Fabrication of Pylons for ALIGO Optical Lever:Contract / PO
Procurements
25 Aug 201009:00 – 10:30SU-314b HLTS Machined Parts:Bid Evaluation
Procurements
 09:00 – 10:00SU-314b HLTS Machined Parts:Contract / PO
Procurements
30 Jul 2010All day/no time
Procurements
 09:00 – 20-Slot PCIe Expansion Backplanes:Change Orders & Modifications
Procurements
 09:00 – 10:3020-Slot PCIe Expansion Backplanes:RFQ/RFP
Procurements
 09:00 – 11:3020-Slot PCIe Expansion Backplanes:Bid Evaluation
Procurements
 09:00 – 11:0020-Slot PCIe Expansion Backplanes:Contract/PO
Procurements
 09:00 – 10:0020-Slot PCIe Expansion Backplanes:Technical Documentation
Procurements
19 Jul 2010All day/no time
Procurements
Seismic Isolation
29 Jun 2010All day/no time75ADV-S096003
None
03 May 2010All day/no time75ADV-S096877
Procurements
31 Mar 2010All day/no time75ADV-S099981
Procurements
22 Mar 201009:00 – 11:00SI-195a BSC Machined Parts - Batch 1:Supplemental Agreement #5 - CANCELLED
Procurements
 09:00 – 12:00SI-195a BSC Machined Parts - Batch 1:Supplemental Agreement #3
Procurements
 09:00 – 11:30SI-195a BSC Machined Parts - Batch 1:Supplemental Agreement #4
Procurements
19 Feb 2010All day/no time
Fabrication
Procurements
Seismic Isolation
 09:00 – 12:30SI-195i BSC Catalog Internal Pod Parts:RFQ
Fabrication
Procurements
Seismic Isolation
21 Jan 2010All day/no time
None
 11:00 – 12:00SI-159/SU-320 aLIGO Portable CMM's:Basic Contract
None
04 Jan 2010All day/no time75ADV-S092401
Procurements
 09:00 – 10:30SI-150c HAM Cross Beam Clamps, Connector & HEPI Adapter:RFQ / RFP
Procurements
 09:00 – SI-150c HAM Cross Beam Clamps, Connector & HEPI Adapter:Contractual Back Up Documentation
Procurements
 09:00 – 11:30SI-150c HAM Cross Beam Clamps, Connector & HEPI Adapter:Contract / PO
Procurements
30 Nov 200909:00 – 11:30FM-107 FMP Fabricate IO Tubes:Suppemental Agreement No. 2
Procurements
03 Nov 2009All day/no time
Procurements
 09:00 – 09:30HAM Support Tube UHV Cleaning:Technical Documents
Procurements
19 Oct 2009All day/no time75ADV-S079930
Procurements
 All day/no time75ADV-S072327
Procurements
 09:00 – PM Labor Contract - Micah Maples:RFP
None
 09:00 – Think Resources Labor Contract - Derrick Tamsing:RFP
Procurements
02 Oct 200909:00 – HAM/BSC L4C Seismometers :Change Orders & Modifications
Procurements
 09:00 – HAM/BSC L4C Seismometers :RFQ / RFP
Procurements
01 Oct 200909:00 – US Dept Energy - Fire and Emergency Support to LHO (PO#75-S078728):Mod-3 FY2013
Procurements
 09:00 – US Dept Energy - Fire and Emergency Support to LHO (PO#75-S078728):Contract/PO
Procurements
 09:00 – US Dept Energy - Fire and Emergency Support to LHO (PO#75-S078728):Mod-1 FY2011
Procurements
 09:00 – US Dept Energy - Fire and Emergency Support to LHO (PO#75-S078728):Mod-2 FY2012
Procurements
25 Sep 2009All day/no time
Procurements
 09:00 – 10:00BSC Small Electromagnetic Actuators:Change Orders & Modifications
Procurements
 09:00 – 09:30BSC Small Electromagnetic Actuators:RFQ / RFP
Procurements
 09:00 – BSC Small Electromagnetic Actuators:Contract / PO
Procurements
19 Sep 2009All day/no time
Procurements
 09:00 – Seismic HAM Chamber Feedthroughs:RFQ/RFP
Procurements
 09:00 – Seismic HAM Chamber Feedthroughs:Contract/PO
Procurements
 09:00 – Seismic HAM Chamber Feedthroughs:Change Order and Modifications
Procurements
19 Jun 2009All day/no time
Procurements
 09:00 – COC Large Optics Containers:Change Order and Modifications
Procurements
 09:00 – 20:00COC Large Optics Containers:RFQ/RFP
Procurements
 09:00 – 11:00COC Large Optics Containers:Contract/PO
Procurements
18 May 200909:00 – HAM & HEPI ADC/DAC Boards:RFQ / RFP
Procurements
 09:00 – HAM & HEPI ADC/DAC Boards:Contract / PO
Procurements
02 Feb 2009All day/no time75ADV-S067630
Procurements
 09:00 – SI-132a HAM Capacitive Displacement Sensors:Technical Documents
Procurements

None
  – 00:00
None
  – 00:00
Procurements
Procurements
 All day/no time
None
 All day/no time
Personnel
Personnel
Procurements
Procurements
 All day/no time
None

DCC Version 3.4.2, contact Document Database Administrators